Future North Natomas Library Fact Sheet
| Groundbreaking |
April 3, 2008 |
| Square footage |
22,645 |
| Special features |
Teen room, two group study rooms, computer lab and classroom |
| Community meeting room |
75-seating capacity |
| Public access computers |
120 |
| Collection(books, periodicals, DVDs, CDs, etc.) |
More than 100,000 items |
| Structural engineers |
Buehler & Buehler Associates, Sacramento |
| Building architects |
Nacht & Lewis Architects, Sacramento |
| Landscaping architects |
MTW Group, Sacramento |
| Furniture design |
Flying Colors, Inc.; Berkeley |
| Lighting contractor |
TEE: The Engineering Enterprise, Auburn |
| Interior signage |
Bess Design, Oakland |
| Total project cost |
$17,300,000 |
| Funding |
Proposition 14 State Bond Act Grant, City of Sacramento Developer Impact Fees, Natomas Unified School District, and Los Rios Community College District |
Project Timeline
| Dates |
Description |
| January 2007 |
Programming & Schematic Design Work Completed |
| April 2007 |
Working Drawings Complete |
| August 2007 |
DSA/State Library review |
| October 2007 |
Contract Documents |
| January 2008 – March 2008 |
Construction Bidding/Award |
| April 2008 – June 2009 |
Construction |
| September 2009 |
Library Grand Opening |
|
|