Sacramento Public Library
Future North Natomas Library Fact Sheet
Groundbreaking April 3, 2008
Square footage 22,645
Special features Teen room, two group study rooms, computer lab and classroom
Community meeting room 75-seating capacity
Public access computers 120
Collection(books, periodicals, DVDs, CDs, etc.) More than 100,000 items
Structural engineers Buehler & Buehler Associates, Sacramento
Building architects Nacht & Lewis Architects, Sacramento
Landscaping architects MTW Group, Sacramento
Furniture design Flying Colors, Inc.; Berkeley
Lighting contractor TEE: The Engineering Enterprise, Auburn
Interior signage Bess Design, Oakland
Total project cost $17,300,000
Funding Proposition 14 State Bond Act Grant, City of Sacramento Developer Impact Fees, Natomas Unified School District, and Los Rios Community College District


Project Timeline
Dates Description
January 2007 Programming & Schematic Design Work Completed
April 2007 Working Drawings Complete
August 2007 DSA/State Library review
October 2007 Contract Documents
January 2008 – March 2008 Construction Bidding/Award
April 2008 – June 2009

Construction
September 2009 Library Grand Opening